The capacity between NO3 and SE (800/550 MW), will be reduced to 600/450 MW between June 1 and July 31, 2009, Statnett told Nord Pool.
One of Nordel's prioritised cross-border reinforcements, the new 420 kV interconnection Nea-Järpströmmen, is planned to be commissioned 2009-08-01.